A 9,000BPH fully automatic pure water bottling and packaging line in Malaysia — from equipment manufacturing and workshop testing to on-site commissioning and operator training, delivered in approximately 90 days.
Project Overview

9000BPH Complete Pure Water Bottling Plant Project in Malaysia

In January 2024, ALPS Machine completed the installation and commissioning of a complete pure water bottling plant for a bottled water manufacturer based in Malaysia. The project involved supplying a fully automatic production and packaging line designed to process pure water in 250ml, 450ml, and 1.4L PET bottles, improve operational efficiency, reduce manual labor, and meet the customer's growing market demands.

The complete pure water plant integrates a water treatment system, automatic PET bottle blowing machine, air conveyor system, filling machine, labeling machine, date printer, and a film packing machine. From equipment manufacturing and factory testing to on-site commissioning and operator training, ALPS Machine provided comprehensive support throughout the project.

图片8_副本.png
Workshop Equipment Testing

Watch the workshop testing of the complete pure water bottling line before shipment.

Project Overview

Project DetailInformation
CustomerBottled Water Manufacturer
LocationMalaysia
IndustryBottled Drinking Water Manufacturing
Project DateJanuary 2024
Project TypeNew Factory Setup
ProductPure Drinking Water
Bottle Size250ml, 450ml & 1.4L PET Bottles
Designed Capacity9,000 Bottles per Hour (for 250ml/450ml) / 3,300 BPH (for 1.4L)
Automation LevelFully Automatic
SolutionComplete Pure Water Bottling and Packaging Line

Customer Requirements

图片9_副本.png


The customer needed a complete, automated bottling solution for its new facility to support the high-volume production and packaging of 250ml, 450ml, and 1.4L pure water bottles. The main objectives were to establish a high-capacity production line, minimize manual intervention, and improve overall operational efficiency and product presentation.

To meet these requirements, the customer needed an integrated system that could seamlessly handle all main production stages, from raw water treatment and bottle blowing to air conveying, precise liquid filling, labeling, date coding, and film packaging. High hygiene standards and reliable, continuous operation were also critical considerations.

ALPS Machine's Complete Water Bottling Solution

ALPS Machine supplied a fully automatic pure water production and packaging line, integrating multiple major types of equipment into one synchronized workflow.

The production line configuration is as follows:

Water Treatment System → Automatic Bottle Blowing Machine → Air Conveyor System → Filling Machine → Labeling Machine → Date Printer → Film Packing Machine

Each machine performs a specific function, allowing bottles to move through the manufacturing process in a smooth, coordinated sequence.

Main Equipment and Functions

What Each Machine Does

图片11.png图片12.png
EquipmentFunction
Water Treatment SystemPurifies raw water through multi-stage filtration to meet strict drinking water standards.
Automatic Bottle Blowing MachineBlows preforms into uniform 250ml, 450ml, and 1.4L PET bottles at high speeds.
Air Conveyor SystemTransports empty PET bottles smoothly from the blower to the filling machine using air pressure.
Filling MachineAdopts an advanced mineral water filling machine structure to execute precise liquid rinsing, filling, and capping.
Labeling MachineApplies product labels securely and accurately onto the bottles for clear branding.
Date PrinterPrints production dates and batch codes clearly on the bottles or caps.
Film Packing MachineAutomatically groups and wrap-packs finished water bottles with PE film for transport.

By integrating these machines, the solution covers the entire spectrum from raw water treatment and bottle preparation to precision filling via a professional automatic mineral water bottle filling machine and secondary film packaging.

Project Implementation Process

1. Production and Testing

The complete bottling and packaging line had a delivery lead time of approximately 90 days after order confirmation. Before shipment, all machines were interconnected and tested at the ALPS Machine workshop to verify their integrated operation. Factory trial runs completed in January 2024 demonstrated high filling precision, stable bottle transport, and excellent overall equipment performance at the customer's factory.

2. Equipment Delivery

After successful factory testing, the equipment was securely packed and transported by sea to the customer's factory in Malaysia, arriving smoothly in accordance with the project schedule.

3. On-Site Installation and Commissioning

Following delivery, ALPS Machine dispatched an experienced on-site engineer to the customer's facility to assist with equipment installation, layout debugging, and system commissioning, ensuring that the heavy-duty mineral water filling plant components and auxiliary units were properly integrated and operational.

4. Operator Training

The ALPS Machine engineer provided professional, hands-on operation and maintenance training for the customer's workers, helping them master standard operating procedures, routine troubleshooting, and safety guidelines.

Project Results

The new water bottling line was engineered to meet the customer's high-volume manufacturing demands for multi-size pure water products. Its integrated configuration offers several major operational advantages:

  • High production capacity: Designed for an output of 9,000 bottles per hour (250ml/450ml), easily accommodating large-scale commercial distribution and peak demand periods.

  • Full-line automation: Seamlessly links bottle blowing, air conveying, filling, labeling, code printing, and film packaging, dramatically reducing labor intensity.

  • Strict hygiene and quality control: Food-grade material is adopted for all liquid-contact parts, and stable liquid levels ensure high batch consistency and defect-free packaging.

  • Reliable commercial performance: Enabled steady mass production, ensuring that product appearance, sealing integrity, and filling volumes met strict international standards.

Customer Feedback

WechatIMG60.jpeg

The customer expressed sincere appreciation to ALPS Machine for supplying the high-quality water bottling equipment and dispatching a professional engineer to support the factory launch.

Management specifically acknowledged the expert on-site debugging service and the comprehensive worker trßaining, noting that the reliable performance of the new line successfully fulfilled their market expansion goals.

Conclusion

The Malaysia pure water project demonstrates ALPS Machine's capability to deliver complete liquid packaging and processing solutions for the global beverage and water treatment sector. By combining custom-engineered equipment with rigorous factory testing, expert on-site commissioning, and thorough operator training, ALPS Machine helps clients build highly automated, efficient production facilities.

For businesses planning a new bottled water factory or looking to upgrade an existing production plant, ALPS Machine offers tailored liquid filling and packaging solutions designed to match specific output goals and factory layouts.

Planning a drinking water bottling plant? Contact ALPS Machine to discuss a suitable mineral water filling machine configuration for your production needs.

Customer Feedback

What Our Clients Say

★★★★★

"We sincerely appreciate ALPS Machine for supplying high-quality water bottling equipment and dispatching a professional engineer to support our factory launch."

Bottled Water Manufacturer
Bottled Drinking Water Manufacturing · Malaysia
★★★★★

"We specifically acknowledge the expert on-site debugging service and comprehensive worker training, noting that the reliable performance of the new line successfully fulfilled our market expansion goals."

Bottled Water Manufacturer
Pure Water Bottling Plant · Malaysia

FAQ

What bottle sizes can this pure water bottling line handle?

This project line was designed for pure water in 250ml, 450ml, and 1.4L PET bottles. The automatic bottle blowing machine, filling machine, labeling machine, and film packing machine work together to process and package these bottle sizes.

What is the production capacity of this pure water bottling line?

The Malaysia project features a fully automatic bottling line with a designed capacity of 9,000 bottles per hour for 250ml and 450ml bottles, and 3,300 bottles per hour for 1.4L bottles.

What equipment is included in the complete pure water production line?

The configuration includes a water treatment system, automatic bottle blowing machine, air conveyor system, filling machine, labeling machine, date printer, and film packing machine.

How long is the delivery lead time?

For this project, the delivery lead time was approximately 90 days after order confirmation. Before shipment, all machines were interconnected and tested at the ALPS Machine workshop to verify their integrated operation.

Does ALPS Machine provide installation and operator training?

Yes. For this Malaysia project, ALPS Machine dispatched an experienced on-site engineer to assist with equipment installation, layout debugging, and system commissioning. The engineer also provided hands-on operation and maintenance training for the customer's workers, covering standard operating procedures, routine troubleshooting, and safety guidelines.

Are the machines tested before shipment?

Yes. All machines were interconnected and tested at the ALPS Machine workshop before shipment. Factory trial runs completed in January 2024 demonstrated high filling precision, stable bottle transport, and excellent overall equipment performance.

Advanced Liquid Packaging Solutions !

×

Drop a line

×

Contact Us

×

Inquire

*Name
*Email
Company Name
Tel
*Message
×

By continuing to use the site you agree to our privacy policy Terms and Conditions.

I agree